Transmission interconnection feasibility study for supplying additional 600 MW power from the existing HUBCO plant to K-Electric under a direct contract or through the wheeling arrangement. The scope includes identifying transmission options, preparation of cost estimates for transmission facilities, techno-economic comparison of transmission alternatives including power flow, short circuit and stability studies.